PROTECTING WILDLIFE Threats to the California red-legged frog could slow down the start of construction on Morro Bay's wastewater facility. Credit: Image Courtesy Of The City Of Morro Bay

The U.S. Department of Fish and Wildlife is conducting another review of the future Morro Bay water reclamation facility site and its potential impacts on the California red-legged frog. The review could lead to potential cost impacts and delays in the project’s construction.

PROTECTING WILDLIFE Threats to the California red-legged frog could slow down the start of construction on Morro Bay’s wastewater facility. Credit: Image Courtesy Of The City Of Morro Bay

“This came, kind of, last minute, but again it’s an important consideration so we’re going to work through it,” Morro Bay City Manager Scott Collins said. “It will mean delaying the project start for several weeks, up to several months, depending on how long the review takes.”

Collins said the city has been working with the Environmental Protection Agency (EPA) in earnest for the past several years in an effort to secure low-interest funding through the Water Infrastructure and Innovation Act for the project. In 2017, the city’s project was chosen for funding out of 12 nationwide applicants.

Because the Water Infrastructure and Innovation Act is federal funding, the project must comply with the requirements of the National Environmental Policy Act—one of the requirements being a review by the U.S. Fish and Wildlife Service under section 7 of the endangered species act.

The review, Collins said, began in June.

On Oct. 10, the EPA received a letter from Fish and Wildlife indicating that the agency did not agree with the EPA’s determination that the project “may affect, but not likely to adversely impact” the California red-legged frog and its critical habitat.

According to the letter, the department’s determination is based on “the proximity of suitable aquatic habitat to the project site, the possibility of California red-legged frogs using Drainage 3 as a dispersal corridor, and the permanent loss of 7.1 acres of upland and dispersal habitat within” the frogs’ critical habitat.

The department requested more information on the project regarding preventative measures to keep frogs out of the project’s detention ponds, the fencing surrounding the projects, nighttime lighting, and how much riparian vegetation will be removed or temporarily disturbed along Morro Creek in order to install a pipeline bridge.

The EPA responded to the agency with the additional information, but Collins said it will be a few weeks before the city will know how long the review will take.

He said the review will temporarily postpone construction, which then leads to cost increases. Construction can’t begin until the review is final.

“You can’t predict what the issue will be, but that’s why you build contingency into your budget because there are unknowns, and this is one of them,” Collins said. “The environmental review is very important because it considers other species that use this land, and we want to be a good neighbor not only to our human neighbors but also wildlife.”

According to city officials, there hasn’t been a red-legged frog occurrence documented within a square mile of the South Bay Boulevard site since 1996.

Failure to comply with this process would nullify federal funding for the project, including the Water Infrastructure and Innovation Act and the Clean Water State Revolving fund. Δ

Local News: Committed to You, Fueled by Your Support.

Local news strengthens San Luis Obispo County. Help New Times continue delivering quality journalism with a contribution to our journalism fund today.

Join the Conversation

2 Comments

  1. According to this article, Morro Bay must now address the red-legged frog habitat issue at the 11th hour because of the federal loan and the sudden and unexpected application of Endangered Species Act (ESA) regulations to this project. The fact of the matter is that the City has always been required to comply with the ESA. The EIR admits the City never conducted appropriate frog surveys, but claimed they were not needed because the site does not contain suitable frog habitat. At long last, the letter from the Fish and Wildlife Service shows this was not true, a fact that was apparently overlooked by the Coastal Commission. Don’t blame the Feds for the delay, blame the City of Morro Bay and the Coastal Commission for giving the Project a false green light in the first place.

  2. The city said a Red-legged frog sighting hasn’t been documented on the site since 1996. Certainly, with all the documentation, more study, and outreach for the viability of this site, Fish and Wildlife could have voiced their concerns earlier. In Oceano, Fish and Wildlife failed to object to vehicular crossings of Arroyo Grande Creek. Now, State Parks is claiming that Steelhead have “disappeared”, so they won’t have to plan for Steelhead protections in their upcoming Habitat Conservation Plan. Why is Fish and Wildlife so late to the party on these important issues?